Guam Cable Landing
For this project the divers were responsible for the following underwater tasks:
The sequence of Events for each HDD punch out
- Removal of blind flange adapter
- Installation of Bell Mouth & preparations of pulling rope
- Removal of Bell Mouth
- Installation of articulated pipe flange adapter
- Installation 6m articulated pipe
All the surveys and observations of pull-in will be performed with ROV.