Guam Cable Landing

For this project the divers were responsible for the following underwater tasks:

The sequence of Events for each HDD punch out

- Removal of blind flange adapter

- Installation of Bell Mouth & preparations of pulling rope

- Removal of Bell Mouth

- Installation of articulated pipe flange adapter

- Installation 6m articulated pipe

All the surveys and observations of pull-in will be performed with ROV.