Dominion Virginia Power

Eltham Marsh Foundation Repair
Contract Value: $2,725,954.00
Duration: 6 Months
Project Manager(s): Zulfikhar Ahmed

Transmission Tower Foundation Repairs. The project Consists of 6 towers located within Eltham Marsh along Pamunkey River in West Point, VA. The scope of work included but not limited to Installation of sheet pile cofferdams, excavation and dewatering, installation of FRP jackets and grouting each foundation pile, forming and placing reinforced concrete foundations for each tower. This project requires both land and marine based operations due to some of the tower foundation located within streams and river. Environmentally very hallenging site and require utmost care in handling impacted areas