Craney Island Bulkhead Replacement
Portsmouth, VA
Contract Value: $1,667,019
Duration: 180 Days
Project Manager: Carlton Diggs
Kinder Morgan Repairs to Berth Bulkhead
Chesapeake, VA
Contract Value: $1,843,124
Duration: 65 Days
Project Manager: Chris Sheets
Bay Oaks Breakwaters
Norfolk, VA
Contract Value: $924,175
Duration: 210 Days
Project Manager: Chris Sheets
Rehabilitation of the Botetourt Pedestrian Bridge
Norfolk, VA
Contract Value: $239,310
Duration: 120 Days
Project Manager: M.Scott Rupe
Replacement of Research Pier
Gloucester Point, VA
Contract Value: $1,361,025
Project Manager: Carlton Diggs
16th and 42nd Streets Pump Station Outfall Repairs
Virginia Beach, VA
Contract Value: $5,861,531
Duration: 547 Days
Project Manager: Larry Crook
Buckroe Beach Fishing Pier Construction
Phase II Decking, Shelters, Ramps, Lighting among other items.
Hampton, Virginia
Contract Value: $1,107,062
Duration: 5 Months
Project Manager: Larry Crook / Carlton Diggs
Underwater Debris Removal from Piers V1 IL & M1 IL
Woodrow Wilson Bridge
Contract Value: $757,888
Duration: 8 months
Project Manager: Joe Anson
NORTH CAROLINA STATE PORTS AUTHORITY
Repairs & Upgrades to Berths 8 and 9
Port of Wilmington
Contract Value: $3,111,693
Duration: 252 days
Project Manager: Larry Crook and Carlton Diggs