U.S.
ARMY CORPS OF ENGINEERS As part of a $400 Million 10-year Rio Puerto Neuvo Flood Control Project, The USACE awarded Precon Marine, Inc. Contract 1A for the Constitution Bridge Seismic Retrofit. This plan of improvements will protect against the 100-year flood by the construction in the Puerto Nuevo River and its tributaries. This $4 Million Constitution Bridge retrofit
project consists of replacing girder bearings and expansion joints, repairing girders, adding
crossframe bracing between girders in various locations, and painting portions of the bridge,
including lead-base abatement and sandblasting. Existing bearings are to be replaced with
new seismic isolation bearings for all girder bearings on Piers 13 and 19. A total of 111
bearings are being replaced in order to address failed bearings and bring the bridge up to
current seismic code. New lines of crossframe bracing between girders are to be added on either
side of Piers 13, 16, and 19 also to bring the bridge up to the current seismic code. The
lines of crossframe bracing are to be installed for the full width of the bridge at each location.
Existing failed expansion joints are to be removed and replaced with new joints for the complete
width of bridge at Piers 13, 16, and 19. The end 3 feet of all bottom girder flange bearings
on the southwest side of Pier 16 and the northeast side of Pier19 are to be replaced due to
deterioration. The project will require jacking up the bridge to repair girders and replace
the bearings. Roadway is to be milled, repaved and restriped. Miramar
Water Transmission Pipeline As a $2,800,000 modification to the original project, Precon Marine, Inc. will perform the installation of a 36” treated water pipeline and appurtenances for the North Coast Water Transmission and Distribution Improvements, San Juan Metro in Puerto Rico. HP14x73 Steel Bearing Piles will support the 1750’ of 36” ductile iron pipeline. With the 388 days added to the original contract time for this modification, the estimated completion date for the project is April 2005.